The permit, first
Oakland says it in its own fire code: when access control devices — "bars, grates, gates, electric or magnetic locks or similar devices, which would inhibit rapid fire department emergency access" — are installed, such devices shall be approved by the Fire Code Official, and they must also comply with Chapter 10, Egress. There is no unreviewed lane for an egress mag-lock in Oakland.
The filing runs on two tracks. The fire side is the Oakland Fire Department's Fire Prevention Bureau (FPB), which provides plan review across all project categories for Fire Code approval. The hardware also rides a building permit through the Planning & Building Department. This page covers the egress mag-lock tied into the fire alarm — the case that pulls both.
The two tracks live in two different systems, and nothing links them automatically. The building permit runs in the Accela Citizen Access Online Permit Center. FPB is not in Accela — fire plan review starts with FPB's plan review / consultation in-take form, submitted to the Bureau (250 Frank H. Ogawa Plaza, Suite 3341). FPB takes prepayment before a review is assigned. Two details that trip out-of-town filers: an Accela account deactivates if the contractor's or business license expires, and FPB resubmittals must reference the prior work-order number. FPB also offers a 60-minute virtual consultation ($717) before you submit plans.
The hardware rules CBC §1010.1.9.x
California's electromagnetic-lock section — the §1010.1.9.x family; the exact subsection number shifts with the adopted CBC edition — sets the baseline, and Oakland's amendment layers the Fire Code Official's approval on top of it:
FPB's in-take package is specific: a site plan and floor plan at 1/8" scale with all door swings and partitions labeled, a riser diagram, a system description, battery and voltage-drop calculations, and cut sheets with listing sheets for the components. Oakland publishes no mag-lock-specific checklist beyond the in-take form — this package is what the Bureau works from.
Two finals close the job OAKLAND FPB
FPB inspection intake requires the approved plans first — there is no scheduling a fire inspection against an unreviewed set. Two inspections close an access-control job: the FIRE ALARM FINAL and the FIRE/BUILDING FINAL. Both are billed by the hour (see the fee table below), which is why the approved set matters: the final is a demonstration against the approved plans, and an install that doesn't match them books another billed inspection.
What the city charges OAKLAND FPB
Oakland publishes its fire inspection rates. Plan review runs on prepayment — FPB does not assign the review until it is paid — and the city does not publish a single mag-lock fee line beyond that.
| Item | City fee |
|---|---|
| FPB fire inspections (incl. FIRE ALARM FINAL and FIRE/BUILDING FINAL) | $500 / hour |
| After-hours inspections | $751 / hour (2.5-hour minimum) |
| Optional pre-submittal virtual consultation (60 minutes) | $717 |
City fees are the city's. PermitsPros passes them through at cost, with receipts — our service is the flat fee beside them, below.
The process, run for you
Intake
Send the drawings and hardware cutsheets (or just the drawings; we build the packet). Signed authorization + photo ID — and we confirm your Accela account and licenses are live before anything files.
FPB package
We assemble the Bureau's in-take package: scaled plans with door swings labeled, riser diagram, system description, battery and voltage-drop calcs, cut sheets and listing sheets.
FPB plan review
Prepayment in, review assigned. Fire Code approval of the devices and the egress compliance — the review Oakland's own amendment requires.
Building permit
The hardware permit issues through Accela, tracked in parallel with the fire record — two systems, one desk watching both.
Install
Your crew installs to the approved set — the set the finals will be demonstrated against.
The finals
FIRE ALARM FINAL and FIRE/BUILDING FINAL with FPB, scheduled and coordinated. Signed-off permit delivered.
One flat number per project, set by how many entries are controlled — quoted up front, never a meter. One corrections round included; additional rounds are $295 each, quoted in writing before we resubmit. City fees at cost, passed through with receipts.
| Entries (doors / openings) | Service fee |
|---|---|
| 1–9 entries | $495 |
| 10–24 entries | $795 |
| 25–49 entries | $1,195 |
| 50+ entries | $1,695 |
Optional: $195 plan code-review (before filing) · $195+ cutsheet packet built for you — the add-ons stay flat at every tier.
Why it matters
Finals are billed by the hour
FPB finals run $500 an hour. A failed final is not a shrug — it is another scheduled, billed inspection, on the Bureau's calendar.
Egress violations
A door that doesn't meet the CBC lock section is a life-safety finding against the building — and the correction belongs to the owner.
Occupancy delays
Corrections run as resubmittals and re-tests on the city's schedule, not yours — a tenant improvement or a move-in waits on a door.
Installed properly per the fire code, none of this is your problem. That is the whole service.
Filed today. You never left the job.
Send the drawings and cutsheets — or just the drawings. We run the in-take, the FPB review, the building permit, and both finals.
Order the permit — $495/siteCheck my city — freeSources
Oakland Fire Department, Fire Prevention Bureau — Fire Prevention Plan Review Services (plan review scope, prepayment, final inspections and rates) — oaklandca.gov · FPB Plan Review / Consultation In-Take Form (rev. 09/18/2025) — oaklandca.gov · Oakland Fire Code amendment — access-control device approval by the Fire Code Official — oakland.legistar1.com · City of Oakland Online Permit Center (Accela Citizen Access) · California Building Code §1010.1.9.x (electromagnetic locks). Requirements summarized from the cited sources as of October 2026; the filed permit is reviewed against the code in force for the job.